The Case · No. 2026-63926-CZ

One culvert. One choice. A court is listening.

The complete record of the fight to keep Seymour Road's stormwater in Seymour Road's drainage system.

The Lawsuit

Ballantyne v. Genesee County Road Commission, Wade Trim & Nashville Construction

Case No. 2026-63926-CZ · 7th Judicial Circuit Court (Genesee County) · Hon. Elizabeth A. Kelly · Plaintiff appearing in pro per.

What we claim

The road's cross-culvert concentrates stormwater onto private land (the surface-water rule and trespass), and the deliberate design decisions that worsen it amount to an uncompensated taking under the Michigan Constitution.

What we're asking

Narrow relief: pause only the final paving and drainage close-out on our stretch until the drainage is reviewed and corrected — the fix the contractor already proposed in change orders that the Road Commission denied.

Where it stands

The court denied an emergency TRO but wrote the relief sought “may be appropriate,” and set a full preliminary-injunction hearing for July 27, 2026.

Timeline

How we got here

Public Documents

Read the filings yourself

We believe in transparency. These are the operative documents in the case.